TNAG-2868-FCO40-4122-Sewage-strategy-in-Hong-Kong-1993 — Page 7

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

CONFIDENTIAL

route of the tunnel; and other ancilliary works.

Preliminary

design of the Principal Collection and Treatment system has been

completed. Detailed design started this month and construction is

planned to start in mid-1994 for completion in early 1997.

5.

The six sewage collection networks which will be connected to

it are Tsuen Wan/Kwai Tsing, North West Kowloon, North and South

Kowloon, East Kowloon, Tseung Kwan O, and Chai Wan/Shau Kei Wan.

So far, with the exception of Tseung Kwan 0, consultancy studies

on each of these networks have been completed. The studies

have in each case identified a number of deficiencies such as

lack of capacity, misconnexions and malfunctioning of treatment

facilities. Detailed planning work is now under way.

Construction has already started on sewage upgrading works in two

of the six areas, and will start in the other four once detailed

planning work has been completed.

6.

The Sewage Strategy Study also identified a number of areas

in which action will be needed, but on a less urgent timescale

than the HPP. These will extend beyond 1997 and the Chinese side

will be consulted on them.

7. These include a number of further regional sewage collection

networks being covered by consultancy studies which are not

connected to the principal collection and treatment system and do

not form part of the HPP. Progress of these studies and the six

connected to the principal collection and treatment system is

summarised in Annex A.

CONFIDENTIAL