account DCA discussions with the HKG, will be LTC 93. Details of
changes from the agreed LTC 93 provision, for example manpower
numbers, equipment disposals and revised support arrangements, will be
costed and where necessary entered in LTC 94 as Alternative
Assumptions (AA). Costings will be required from budget areas other
than the Hong Kong HLB, since the costs of operating the Garrison are
borne on a number of TLBS. This process will require close control and
co-ordination through the
the LTC mechanisms as LTC 94 advances. [A
provisional assessment of the funding implications of the 1993 Review,
in advance of the LTC 94 work, is at Annex C.] [[It is intended that
will be included in the HODS Draft of the 1993 Review.
although the information may not be presented in this form. The final
format to be adopted for the HODS and CO5 drafts will be subject to
advice from AUS(CF)]]
Annex
HONG KONG GARRISON WITHDRAWAL PLAN
47.
The planning and implementation lead times for the actions and
activities necessary to effect the Garrison's withdrawal from Hong
Kong by 30 June 1997 are such that preparation of the detailed Hong
Kong Garrison Withdrawal Plan by HQBF HK should now begin, based on
the policy guidance provided in this 1993 Review. Updating of the
threat context in which this Plan will be set should be achieved by
the maintenance for as long as necessary of the integrity of an all-
source intelligence capability in JSIS at a level commensurate with
CBF's intelligence requirements. Allied to the Hong Kong Garrison
30