15-JUL-1774
DRATION TRADE CONNT
Airport Rail Link To be built by the MTRC.
Metro Cammell (now part
of GEÇ Alsthom) have supplied all the rolling stock for Hong
Ong's railways to date and will be bidding to supply the trains.
Other British companies involved in the construction of the MTRC and
KCRC networks, such as Balfour Beatty, Costain and AMEC will also be
bidding when tenders are called.
Western Harbour Crossing: Costain and Tarmac submitted a detailed
proposal to The Wharf Company to build and operate the third harbour
crossing. The Wharf Company have however withdrawn their application
for a franchise and it seems unlikely that British contractors will
now be involved in this project.
New Territory Landfill projects: Both Gammon and AMEC in separate
groups are bidding for these large contracts (HK$8.8 billion in total)
which will be awarded later this year.
Jardine Pacific and MTL are
Contract has yet to
Container Port Terminal 9 Development:
bidding in separate groups to build Terminal 9.
be awarded.
The work is thought to be worth about HK$9 billion.
lack Point Power Station (CLP/Exxon): This will be a combined cycle lack
gas fired station using natural gas from a new gas field south of
Hainan Island. Contract value is in the region of £600 million for
the generating equipment (or £1.4 billion for the complete station,
Competition for the turbines lies between GEC
including equipment).
Alsthom and Diemens of Cezmany. Balfour Beatty will be bidding for
the power line contract and Babcock for the boilers. Bids are due in
at the end of this month. A letter of intent is likely to be signed
before the end of 1992.