TNAG-2415-FCO40-3517-Hong-Kong-Port-and-Airport-Development-Strategy-(PADS)-fina-1993 — Page 56

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

List of Contracts for New Airport and Related Projects

Brief Scope of Contract

Prequalification (P) and Tender (T) Invitation Date

Commencement/ Completion Date

Managing Department/ Officer-in-Charge

Report Date: 18 November 1992

Contractor/

Contract Sum

$M (MOD)

Origin of Contractor

Funding Source/ PWP No.

4.

Lantau Fixed Crossing - Supplemental Site Investigation at the Lantau Toll Plaza (Contract No. HY/92/19)

21 August 1992 (T)

28 October 1992

to

Highways Department (Mr D S Paterson - 802 1340)

10 February 1993 (underway)

Geotechnics and Concrete Engineering (HK) Ltd. $2.455 M (including $ 0.25 M contingency and $ 0.025 M Provisional Sum)

HK

2002AX

5.

Lantau Fixed Crossing - Kap Shui Mun | 16 November 1990 (P) Bridge and Ma Wan Viaduct - a bridge | 4 November 1991 (T) of 671 metres carrying road and rail

traffic from Ma Wan to North Lantau

to be constructed on a design and build

basis. The viaduct will link the bridge to the Tsing Ya Bridge. (Contract No. HY/91/19)

May 1997 (awarded)

December 1992

to

Highways Department (Mr E J Roblin - 802 1328)

Kumagai-Maeda-Yokogaw

Japan/

488TH

a Bridge-Hitachi Zosen

Japan/

J.V.

Japan/

$ 1,643 M

Japan

6.

Lantau Fixed Crossing - Lantau Toll Plaza Eathworks (Contract No. 4A)

January 1993 (P) May 1993 (T)

August 1993

to

Highways Department (Mr D S Paterson - 802 1340)

$ 445 M (UBIP-1 Estimate)

476TH

August 1994

7.

Lantau Fixed Crossing - Traffic Control and Surveillance Systems (Contract No. HY/92/24)

23 October 1992 (P) March 1993 (T)

November 1993

to

Highways Department (Mr H C Fan - 802 1316)

$ 484 M

476TH

(UBIP-1 Estimate)

May 1997

8.

Lantau Fixed Crossing - Electrical & Mechanical Systems (Contract No. 5A)

February 1993 (P)

May 1994

| October 1993 (T)

to

Highways Department (Mr H C Fan - 802 1316)

$ 308 M (UBIP-1 Estimate)

488TH

May 1997

Route 3

1.

Route 3 - site investigation for tunnels (Contract No. HY/90/07)

15 August 1990 (T)

5 September 1990

to

Highways Department (Mr C K Wong - 762 3622)

Gammon Construction

HK

339TH

Ltd.

1 March 1991 (completed)

$ 13.94 M

2.

Route 3 - site investigation for road

15 August 1990 (T)

24 September 1990

aligment (CRA1 route) between Ting Kau and Sham Shui Po (Contract No. HY/90/06)

to

24 March 1991 (completed)

Page No. 4

Highways Department (Mr C K Wong - 762 3622)

Bachy Soletanche Group $ 14.24 M

France

339TH

Comments