List of Contracts for New Airport and Related Projects
Brief Scope of Contract
Prequalification (P) and Tender (T) Invitation Date
Commencement/ Completion Date
Managing Department/ Officer-in-Charge
Report Date: 18 November 1992
Contractor/
Contract Sum
$M (MOD)
Origin of Contractor
Funding Source/ PWP No.
4.
Lantau Fixed Crossing - Supplemental Site Investigation at the Lantau Toll Plaza (Contract No. HY/92/19)
21 August 1992 (T)
28 October 1992
to
Highways Department (Mr D S Paterson - 802 1340)
10 February 1993 (underway)
Geotechnics and Concrete Engineering (HK) Ltd. $2.455 M (including $ 0.25 M contingency and $ 0.025 M Provisional Sum)
HK
2002AX
5.
Lantau Fixed Crossing - Kap Shui Mun | 16 November 1990 (P) Bridge and Ma Wan Viaduct - a bridge | 4 November 1991 (T) of 671 metres carrying road and rail
traffic from Ma Wan to North Lantau
to be constructed on a design and build
basis. The viaduct will link the bridge to the Tsing Ya Bridge. (Contract No. HY/91/19)
May 1997 (awarded)
December 1992
to
Highways Department (Mr E J Roblin - 802 1328)
Kumagai-Maeda-Yokogaw
Japan/
488TH
a Bridge-Hitachi Zosen
Japan/
J.V.
Japan/
$ 1,643 M
Japan
6.
Lantau Fixed Crossing - Lantau Toll Plaza Eathworks (Contract No. 4A)
January 1993 (P) May 1993 (T)
August 1993
to
Highways Department (Mr D S Paterson - 802 1340)
$ 445 M (UBIP-1 Estimate)
476TH
August 1994
7.
Lantau Fixed Crossing - Traffic Control and Surveillance Systems (Contract No. HY/92/24)
23 October 1992 (P) March 1993 (T)
November 1993
to
Highways Department (Mr H C Fan - 802 1316)
$ 484 M
476TH
(UBIP-1 Estimate)
May 1997
8.
Lantau Fixed Crossing - Electrical & Mechanical Systems (Contract No. 5A)
February 1993 (P)
May 1994
| October 1993 (T)
to
Highways Department (Mr H C Fan - 802 1316)
$ 308 M (UBIP-1 Estimate)
488TH
May 1997
Route 3
1.
Route 3 - site investigation for tunnels (Contract No. HY/90/07)
15 August 1990 (T)
5 September 1990
to
Highways Department (Mr C K Wong - 762 3622)
Gammon Construction
HK
339TH
Ltd.
1 March 1991 (completed)
$ 13.94 M
2.
Route 3 - site investigation for road
15 August 1990 (T)
24 September 1990
aligment (CRA1 route) between Ting Kau and Sham Shui Po (Contract No. HY/90/06)
to
24 March 1991 (completed)
Page No. 4
Highways Department (Mr C K Wong - 762 3622)
Bachy Soletanche Group $ 14.24 M
France
339TH