List of Consultancies for New Airport and Related Projects
Table of Content
CONFIDENTIAL
Report Date: 17 Decem 1992
2.
The list includes completed consultancies, current consultancies, and future consultancies which are scheduled to commence in the next 12 months.
Consultancies on the new airport and the airport railway are based on the latest information provided by the Provisional Airport Authority and the Mass Transit Railway Corporation.
3. Project departments please update the agreement fee column for completed
consultancies.
Project
Chek Lap Kok Airport
Page No.
Note:
1.
1
Tung Chung Development Phase I
2
ભેં
North Lantau Expressway
2
Lantau Fixed Crossing
3
Route 3
5
West Kowloon Reclamation
5
West Kowloon Expressway
5
Western Harbour Crossing
6
Central and Wanchai Reclamation
6
Airport Railway
6
Utilities
13
Financial and Legal
14
Miscellaneous
15