Water Supplies
Brief Scope of Contract (and Contract No.)
1. Temporary Water Supply to North Lantau -
Mainlaying from Cheung Sha to Pak Kung Au (Contract No. 24/WSD/90)
Contract award
Dates
6 September 1991
Contractor/ Contract Sum $M (MOD)
Chun Wo
Construction and Engineering Co. Ltd.
$6.4M
2. Temporary Water Supply to North Lantau Construction of Tai Tung Shan Service Reservoir (Contract No. 32/WSD/90)
1 November 1991
Yick Hing Construction Co.
$11.93M
Note: Contracts on the new airport and the airport railway are based on the latest information provided
by the Provisional Airport Authority and Mass Transit Railway Corporation. Estimated final contract sums are at money of the day prices.
∞
?