List of Contracts for New Airport and Related Projects

Brief Scope of Contract

West Kowloon Expressway

14. West Kowloon Reclamation - Hinterland

Drainage Package 2 (Contract No. UA 15/92)

15. West Kowloon Reclamation Sewage

Network - Package 1 (Contract No. UA 16/92)

Prequalification (P) and Tender (T) Invitation Date

24 July 1992 (P) January 1993 (T)

Commencement/ Completion Date

March 1993

to

September 1995

Managing Department/ Officer-in-Charge

Territory Development Department (Mr K Austin - 882 7190)

Contractor/ Contract Sum $ M (MOD)

$ 157 M (BIP Estimate)

December 1992 (P) April 1993 (T)

June 1993

to

March 1995

Territory Development Department (Mr S O Chan - 882 7195)

$ 90 M

+

$ 60 M (From EPD)

as at 1st Oc

Origin of Contractor

r, 1992

Funding Source/

PWP No.

332CL

332CL

16. West Kowloon Reclamation - Reprovision December 1992 (P) of Jordan Road Ferry Pier. (Contract No. | April 1993 (T) CV/92/08)

July 1993

to

May 1995

Civil Engineering

332CL

Department (Mr Y C Lo - 762 5511)

$ 100 M (BIP Estimate)

1.

West Kowloon Expressway - North Section - Cherry Street to Mei Foo (Contract No. HY/92/17)

2 October 1992 (P) February 1993 (T)

June 1993

to

September 1996

Highways Department (Mr R H Lloyd - 507 3952)

$ 1,403 M (BIP Estimate)

332CL 457TH

2.

West Kowloon Expressway - South Section - Western Habour Crossing to Cherry Street and Yau Ma Tei interchange (Contract No. HY/92/18)

Western Harbour Crossing - financing, designing, constructing and operation of a 2 km tunnel crossing of the Victoria Harbour between West Kowloon and Sai Ying Pun. The tunnel will accommodate a dual three-lane road.

2 October 1992 (P) March 1993 (T)

July 1993

to

September 1996

Highways Department (Mr R H Lloyd - 507 3952)

$ 889 M (BIP Estimate)

332CL 457TH

28 February 1992 (T)

August 1993

to

June 1997

Transport Branch (Ms E Cheng - 810 2558)

$ 4,150 M

(Private)

Highways Department

Western Harbour Crossing

1.

Central & Wanchai Reclamation

1.

Central and Wanchai Reclamation Development Package I - Phase I - site investigation (Contract No. UA 2/90)

November 1991 (T)

21 February 1992

to

18 August 1992 (Completed)

(Mr R H Lloyd - 507 3952)

Territory Development Department (Mr H H Yeung - 882 7204)

Bachy Soletanche Group $ 20.73 M

France

353CL