Site Investigation
NEW AIRPORT AND RELATED PROJECTS
LIST OF CONTRACTS COMPLETED
as at 1 June 1992
Brief Scope of Contract
(and Contract No.)
Prequalification and Tender Invitation
Date
Contract award/ Completion
Dates
Managing Department/ Officer In-charge
Contractor/ Contract Sum $M
Origin
Funding Source/
PWP No.
1. Lantau Fixed Crossing Site Investigation
Phase 5 (Contract No. HY/89/33)
15 December 1989
March 1990
to
November 1990
Highways Department (Mr K S Leung - 802 1315)
Gammon/Bachy
Soletanche Joint
HK France
89TH
Venture
$38.2M
2. Route 3 - site investigation for road
aligment (CRA1 route) between Ting Kau and Sham Shui Po (Contract No. HY/90/06)
15 August 1990
to
24 September 1990 Highways Department
(Mr C K Wong - 721 6792)
Bachy Soletanche France
$15.5M
339TH
|24 March 1991
3. Route 3 - site investigation for tunnels
(Contract No. HY/90/07)
15 August 1990
5 September 1990
Highways Department
to
(Mr C K Wong - 721 6792)
Gammon Construction
HK
339TH
1 March 1991
$14.5M
4. West Kowloon Reclamation
7 September 1990
Site Investigation (Contract No. UA 3/90)
19 October 1990
to
Territory Development Department
Lam Geotechnics
Ltd
HK
354CL
19 March 1992
5. North Lantau Expressway Site Investigation
Phase 1 (Contract No. HY/90/23)
15 September 1990
|November 1990
to
(Mr K Austin - 882 7190)
Highways Department (Mr C H Wan - 721 6540)
$36.98M
May 1991
Geotechnics & Concrete Engineering (HK) Ltd.
HK
468TH
$18.5M
6. West Kowloon Reclamation - Short term
flow survey of existing drainage system (Contract No. UA 6/90)
7. North Lantau Development Site
Investigation - Preliminary Report Stage (Contract No. IS 11/90)
25 September 1990
22 February 1991
to
Territory Development Department
Delta Surveys Ltd UK
$1.5M
354CL
30 July 1991
(Mr K Austin - 882 7190)
[25 October 1990
December 1990
to
Territory Development Department
Enpack (HK) Ltd. |HK
352CL
$7.73M
March 1991
(Mr T D Armour - 882 7250)