TNAG-2414-FCO40-3516-Hong-Kong-Port-and-Airport-Development-Strategy-(PADS)-fina-1992 — Page 32

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

NEW AIRPORT AND RELATED PROJECTS

LIST OF CONSULTANCIES TO COMMENCE IN THE NEXT TWELVE MONTHS

as at 1 July 1992

Brief Scope of Consultancy

Expected Commencement Date

Managing Department (Officer In-Charge)

Nationality (Origin) of Consultant

Agreement Agreement No./ Completion Date

Funding

Highways

1. Lantau Fixed Crossing -

1 September 1992

Consultancy for Contracts 4 (Lantau Approach Roads and Toll Plaza) and 5 (E & M Works)

Highways Department (Mr D S Paterson - 802 1340)

To be determined

Type/ Current Est. Fees ($M)

CE 20/92

Source/

PWP No

488TH

Management

1. North Lantau Expressway - Provision of

Construction Management support services to Project Management Office.

To be determined

Highways Department (Mr K C Yeung - 721 6927)

To be determined

D (Pending)

Specialist Staff Services

To be determined

Environ-

mental Monitoring

1. Environmental Protection Office (ENPO) - Environmental monitoring and audit of West Kowloon Project Area

September 1992

Environmental Protection Department

|(Mr M Nash - 835 1131)

September 1994

CE 4/92 Environmental Monitoring

$20M

366 CL

Water

Supplies

1. Pumping main from NLE utility service road August/September 1992

to Tung Chung Fresh Water Service Reservoir -Detailed Design

Water Supplies Department (Mr S K Fong - 829 4467)

To be

determined

Specialist Engineering

2. North Lantau Water Supply

- Detailed Design for

Fresh Water & Salt Water Distribution Mains Stage I Phase I

1. Airport at Chek Lap Kok -

To consult on documentation, tendency, procurement, selection & installation of Air Traffic Control Equipment to support the new airport.

May 1993

WaterSupplies Department (Mr S K Fong - 829 4467)

To be

determined

175WF

D $0.7M

175WF

D

$1.7M

August 1992

Civil Aviation Department (Mr Peter Bodiley - 867 4250)

To be

determined

To be determined

To be determined

Comments