NEW AIRPORT AND RELATED PROJECTS LIST OF CONTRACTS AWARDED

February 1992

Brief Scope of Contract

Prequalification and Tender Invitation

Date

Contract award/ Completion

Dates

Managing Department/ Officer In-charge

Contract

No.

Contractor/

Contract Sum $M

Funding Source/

PWP No.

Civil Engineering

1. West Kowloon reclamation - Construction

of Yau Ma Tei Replacement Typhoon Shelter Phase I (Contract No. CV/90/04)

2. Airport Advance Works

(Contract No. PAA 02/90) - formation of 29ha of land including 15 ha of reclamation, construction of a 650m long seawall, in the bay area of northern Chek Lap Kok to provide a site to house workers' accommodation and other facilities as

preparatory works for the airport construction.

15 June 1990

24 August 1990

to

Civil Engineering Department

CV/90/04 Gammon

146CL

Construction

19 June 1992

(Mr Y C Lo 762 5511)

Ltd.

$234.82M

16 November 1990

28 January 1991

to

-

Provisional Airport Authority |PAA 02/90| Kumagai – Ham –

Maeda (Mr P Leung - 802 3490)

PAA

April 1992

$310.8M

3. West Kowloon Reclamation

Construction

28 December 1990

9 July 1991

to

6 November 1993

of Yau Ma Tei Replacement Typhoon Shelter Phase II and Jordan Road Reclamation Phase I

(Contract No. CV/90/09)

- construction of about 4,000m of vertical seawall/revetment, reclamation of about 69ha of land and reprovisioning of a public cargo working area. The reclaimed land is to provide the landfall for the Western Harbour Crossing, other airport related transport infrastructures and other urban development.

Civil Engineering

Department

(Mr Y C Lo - 762 5511)

CV/90/09 | Shui on

Boskalis

Joint Venture

$1097.29M

146CL

365CL