TNAG-2412-FCO40-3507-Hong-Kong-Port-and-Airport-Development-Strategy-(PADS)-pres-1992 — Page 61

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

OVERALL COSTS (Paper handed 1992. Handed to ACC on 2 April)

Main features

*

-*

over to Chinese on 27 March

The total cost of the ACP has gone up since July 1991 from $98.6 BN to $112.2 BN (1991). The net increase in real terms in the cost of the ACP is $13.6 BN or 13.8%

The cost to the Government (direct works contract costs and equity investments) has not gone up : it remains at $59.3 BN (1991) made up of $45.6 BN in public works costs plus $16.6 BN (1991) in paid up equity, minus

$2.9 BN (1991) in reimbursements from the MTRC.

The present and future Governments will need to accept some commercial investment risk in the form of a commitment to callable equity for the MTRC and the AA.

overall

shall

need an

We now estimate we additional

ACP contingency allowance of $2.5 BN (1991) to cover contract delay and interface problems for the Government projects in the ACP.

Points to make

*

*

*

We have now reached a more advanced planning stage. We have more confidence in these figures than last year's ones. We believe future increases in the cost of Government works can be kept within an overall contingency allowance of $2.5 BN (i.e. to within $2.5 BN of the $45.6 BN to be spent by Government on public works.)

We

have set up a system. The degree greater than for projectsin the past.

rigorous cost control of discipline is much normal public works

It would be unrealistic these costs were final.

to suggest that

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.