XM (92) 42

SEORET

437

the longer we delayed, the worse the congestion would

become.

4.

The

Central-Tsing

three

years

West Kowloon

part of the

Secretary for Transport said the

Yi railway link would be needed in about

time, soon after the completion of the

reclamation. He added, however that the

Airport Railway project that contributed

most in terms of financial justification was the

sector from Tsing Yi to Chek Lap Kok. The Financial

Secretary said this made the shorter railway project

more difficult to justify as a separate entity than as

part of the overall airport railway project.

is not also

allen our

se

vigrind

for abandoning mar and marny naval basin to the cutters?

5.

One

The Governor said he would be happier if we

sounded out the Chinese side only on the six hectares

required to build the Airport Railway Terminus in case

there is a need to give this area some priority.

Member queried whether this would weaken our case with

the Chinese as the revenue from land premia for the

terminal area would be significantly less than that

The amount of money going

the SARG Land Fund would therefore be understated.

Financial Secretary said this was the case but the

sum would still be substantial and attractive.

from the whole reclamation.

to

The

suggested we now

on this basis.

He

approach the Chinese for a reaction

Comments