in both directions, two dual crossfield taxiways connecting the runways and a single parallel taxiway on the southern side of the southern runway. The separation between the runways, centreline to centre- line, will be 11525m.

Taking into account local meteorological conditions, runway and taxiway lighting, ap- proach lighting and navigational aids will be provided to optimize use of the runways. This includes an instrument landing system with the capability of upgrading the service. to a microwave landing system. as this equipment becomes standard.

Approximately 490 hectares or 40% of the total airport site is required for the runways, taxiways and associated equipment, and land reserved for obstacle clearance.

The runway and taxiway system was

selected as a result of a series of com- prehensive analyses. The initial evaluation focused on funway orientation, alignment and separation. A total of 121 options were considered. The evaluation considered the

extent to which terrain cuts might be re- quired to ensure acceptable approach and departure procedures could be devised. together with implications regarding run- way capacity! The 1,525m runway separa- tion was ultimately selected because it provides a greater likelihood of allowing fully independent operations to be con- ducted, thus maximizing potential capacity. The creation of adequate space between the runways for the passenger terminal complex was an important consequence of the separation decision.

A series of Hetailed computer simulation analyses to determine hourly capacities of the runway and taxiway system was con- ducted. The practical hourly capacities as- sociated with alternative methods of

operating the runways were found to vary from 52 to 85 hourly aircraft movements. taking into account the anticipated development of aviation technology. It was concluded that the forecast demand

for the year 2040 of 82 aircraft operations

Airport Reclamado

Sea Channel

Lantau Island

Area (hectares)

Chek Lap Kok Lam Chau

Reclamation

300

8

Total

940

1.243

Tung Chung

Airport Site

OTR

3,800 x

Northern Runway

Chek Lap Kok Island

Tung Chung Reclamation

Southern Runway

Rapid Exit

Sea

Channel

Single Pa Taxiwa

Lantau Island

Runways and Taxiways

per hour could be served by the planned runway and taxiway system.

The geometry of the runways and taxiways. and the runway separation, was based on dimensional criteria proposed by the Inter-

0 300 600 900 m

300 600 900 m

national Civil Aviation Organization. This set of international standards incorporates the requirements of large. high-capacity aircraft currently under design.

25

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.