Cost Plan

Element

1. Substructure

2. Superstructure

2A Frame

2B Upper floor and stairs

2C Roof

2D External walls

2E Windows and external doors

2F Partitions and internal doors

2G Internal finishings

2H Fittings

Total of Element 2

3. Services

3A Sanitary Appliances & Waste

3B Water Installations

3C Mechanical Installation inc A/C & H&CW

3D Electrical installation

Total of Element 3

4. Preliminaries

4A Ancillary buildings

4B Drainage services

4C Hard £ sqft landscaping

4D Other works

Total of Element 4

Sub - total

and Price and Design Risk : 10 %

Contract total

and Contigencies: 6%

PROJECT TOTAL

Annex F

Outline Cost Plan.

Cost of

sub element

£(k)

Total cost

of element

Cost per m2

£(k)

gross floor area £/m2

£/sqm