For issue: Tuesday, October 22, 1991

Hong Kong's New Airport Terminal Building Design Invitation To Tender

In response to enquiries, the Provisional Airport Authority said today that eight groups have been invited to tender for the Terminal Building Design Contract.

The authority said that the invitations had gone to the following groups:

Greiner/N&A/HOK

Leo A.Daly

The Mott Consortium

1.

2.

3

4.

P&T and JSKPWI

5.

Parsons (RMP Enoon)

8.

SSWP

7.

Wong & Ouyang/Skidmore, Owings and Merrill

8.

YRM Partnership Limited

The make-up of these groups is detailed in the attached appendix.

A spokesman for the Provisional Airport Authority said that it was planned to issue tender documents to the selected tenderers within the next week and to receive tenders by the end of the first week in December. Work should start in March 1992.