TNAG-2251-FCO40-3235-Hong-Kong-Port-and-Airport-Development-Strategy-(PADS)-fina-1991 — Page 20

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

NEW AIRPORT AND RELATED PROJECTS

LIST OF CONSULTANCIES TO COMMENCE IN THE NEXT TWELVE MONTHS

1 October 1991

Airport

Brief Scope of Consultancy

1. Passenger Terminal Complex Detailed

Design Consultancy - prepare detailed architectural and engineering design work required for the passenger terminal at the new airport

Expected Commencement Date

Managing Department (Officer In-Charge)

Nationality

(Origin)

Agreement Agreement No./ Completion Type/Fees ($M)

Funding

Source/

Date

PWP No

Consultant

December 1991

Provisional Airport Authority (Mr Peter Wright - 802 3419)

12.93

PAA

IDC

Highways

1. Lantau Fixed Crossing - Lantau

Approach Road including Toll Plaza (may include Toll Collection System)

2. Lantau Fixed Crossing -

Traffic Control & Surveillance System

October 1991

Highways Department (Mr KH Lee - 721 4307)

4.98

DC

2002AX & 476TH

$20M

November 1991

Highways Department (Mr KH Lee - 721 4307)

4.98

DC $15.8M

2002AX & 476TH

Water Supplies

1. Water Supply to North Lantau and raw

water transfer to Silvermine Bay Treatment Works

October 1991

Water Supplies Department (Mr CH Ng829 4408)

6.9%

CE 12/91

2005AX

IDC

$29.81M

$6M funded by

non-PADS item

172WF

3

Management 1. Airport and Related Projects Overall

Works Management - Phase II

January 1992

(Mr A Fung 829 6780)

-

Works Branch

N/A

Management