Order of cost provided to the Chinese (Option 1)
Project
$ billion at 1990 prices
$ billion at March 1991 prices
Current order of cost in $ billion at March 1991 prices
CLK airport
37.8
41.2
43.6
North Lantau
5.0
5.5
4.3
Expressway
W Kowloon
9.5
10.4
9.0
Reclamation
W Kowloon
2.5
2.7
1.7
Expressway
W Harbour
4.1
4.5
3.9
Crossing
Route 3 (part)
5.1
5.6
5.6
Lantau Fixed
10.3
11.2
12.1
Crossing
Tung Chung
3.1
3.4
2.6
Development.
Phase I
Utilities
2.0
2.2
1.5
Airport Railway
14.5
15.8
12.5
Central &
3.1
3.4
1.8
Wanchai
Reclamation
Tot
97.0
105.7
98.6