NEW AIRPORT AND RELATED PROJECTS

LIST OF CONTRACTS AWARDED

1 Aug 1991

Brief Scope of Contract

Tender Invitation

Date

Contract award/ Completion Dates

Civil

Engineering

1. West Kowloon reclamation – Construction of

Yau Ma Tei Replacement Typhoon

15 June 1990

24 August 1990

Civil Engineering Services

to

19 June 1992

Department (Mr CLAu

368 5692)

Managing Department/ Contract

Officer In-charge

No.

CV/90/04 Gammon

Construction Ltd.

Contractor/ Contract Sum $M

Funding Source/ PWP No.

146CL

$234.82M

28 January 1991

to

Provisional Airport Authority PAA 02/90 Kumagai - Ham (Mr P Leung 802 3490)

Macda

PAA

29 January 1992

$310.8M

Site Investigation

Shelter Phase I

2. Airport Advance Works - formation of 29ha of 16 November 1990.

land including 15 ha of reclamation,

construction of a 650m long seawall, in the bay area of northern Chek Lap Kok to provide a site to house workers' accommodation and other facilities as preparatory works for the airport construction.

3. West Kowloon Reclamation - Construction of Yau Ma Tei Replacement Typhoon Shelter Phase II and Jordan Road Reclamation Phase I (Contract No. CV/90/09) — construction of about 4,000m of vertical seawall/revetment, reclamation of about 69ha of land and reprovisioning of a public cargo working arca. The reclaimed land is to provide the landfall for the Western Harbour Crossing, other airport related transport infrastructures and other urban development.

4. West Kowloon Reclamation – Northern Arca

Phase I (Contract No. UA5/90) – reclamation of about 38ha and construciton of 1700m of seawall adjacent to Tai Kok Tsui/Sham Shui Po to provide land for the West Kowloon Expressway, the airport railway and other developments as well as construction of

replacement ferry piers and marine facilities including market and cargo-handling piers.

28 December 1990.

9 July 1991

Civil Engineering Services

to

6 November 1993

Department (Mr CLAu

368 5692)

CV/90/09 Shui on/ Boskalis

joint venture

$1097.29M

146CL

365CL

11 January 1991

17 July 1991

to

1 May 1993

l'erritory Development Department (Mr K Austin 848 2668)

UA 5/90 Kumagai - Ham

366CL

Maeda

$1553.9M

1. West Kowloon Reclamation Site Investigation 7 September 1990

19 October 1990

to

18 October 1991

Territory Development Department (Mr K Austin - 848 2668)

UA 3/90 Lam Geotechnics

Ltd

354CL

$35.98M

Comments