TNAG-2146-FCO40-3065-Hong-Kong-Port-and-Airport-Development-Strategy-(PADS)-1990 — Page 180

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

2 -

airport open in 1997.

bridges,

reclamation.

the

links

These are the airport itself, the transportation

and associated

Some of these projects, for example, the West Kowloon reclamation and expressway, would have been required even without the airport.

The estimated order of costs of these key airport projects is as follows :

Project

Order of cost

($ million at 1990 prices in period to 1997)

W Kowloon Reclamation

W Kowloon Expressway

W Harbour Crossing

9,500

2,500

4,000

Route 3 (part)

5,000

CLK Airport

38,000

N Lantau Expressway

5,000

(incl. rail reserve)

Tung Chung development phase I

3,000

Lantau Fixed Crossing

two bridges

7,000

rail portion & Route 3

interchange

Utilities & Other Miscellaneous

3,000

2,000

79,000

(Caution should be

exercised in the interpretation of these

order of costs as most of the projects are currently at the preliminary design stage, and the figures do not include allowance for contingencies. The Airport Railway has also been excluded. A study of the railway is currently in hand, which will review the scope and target commissioning date of the project. A decision will be announced in early 1991.)

Page 180Page 181