TNAG-2146-FCO40-3065-Hong-Kong-Port-and-Airport-Development-Strategy-(PADS)-1990 — Page 139

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

6. Central and Wanchai Reclamation - Phase I -

reclamation of about 40 ha and construction of

around 1,110 metres of seawall between Rumsey Street and Tamar to provide land for the expansion of the Central Business Area and the Airport Railway Terminus as well as construction of replacement ferry piers and air conditioning intake facilities.

April 1991

Territory Development Departme

(Mr K Austin - 848 2668)

Highways 1. Route 3 Sector between Kwai Chung and Lai Chi Kok - construction of approx. 4 km of a dual 4-lane highways on clevated strctures.

May 1991

12.

August 1991

|November 1991

March 1991

Projects

North Lantau Expressway, Tai Ho Section - construction of about 6 km of a dual three-lane

highways on north Lantau, including site formation for the twin-track airport railway.

3. North Lantau Expressway, Yam O Section –

construction of about 4 km of a dual three-lane

highways on north Lantau, including site formation for the twin-track airport railway.

Privatization 1. Route 3 Sector between Kwai Chung and Ting

Kau - possible bid package for financing, designing, constructing and operation of about 6 km of dual-three lane roads on a cable stayed high level bridge, elevated structures, bored tunnels, and a medium level bridge.

2. Western Harbour Crossing - bid package for

financing, designing, constructing and operation of a 1.5 km tunnel crossing of the Victoria Harbour between West Kowloon and Sai Ying Pun. The

tunnel may accommodate a dual three-lane The tunnel may accommodate a dual three-lane road and possibly also a twin-track railway.

April 1991

Highways Department

(Mr H S Kwong - 733 2508

Highways Department

(Mr K S Leung - 721 6540)

Highways Department

(Mr KS Leung – 721 6540)

Highways Department

(Mr H S Kwong – 733 2508

Highways Department

(Mr J M Turner – 573 3885!

Site

Investigation

1. Route 3 site investigation for road aligment

September 1990

(CRA1 route) between Ting Kau and Sham Shui Po.

2. North Lantau Expressway - site investigation for September 1990

new alignment..

3. Central and Wanchai Reclamation - Phase I site October 1990

investigation for Phase I reclamation and maraine borrow area.

4. Route 3 site investigation for highways

February 1991

between Tai Lam Country Park and Au Tau.

Highways Department

(Mr H S Kwong – 733 2508

Highways Department (Mr K S Leung – 721 6540)

Territory Development Department

-

(Mr K Austin – 848 2668)

Highways Department

(Mr H S Kwong - 733 2508

1