TNAG-2146-FCO40-3065-Hong-Kong-Port-and-Airport-Development-Strategy-(PADS)-1990 — Page 133

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

Highways

8 October 1990

NEW AIRPORT AND RELATED PROJECTS

LIST OF CONSULTANCIES ENVISAGED TO START IN NEXT TWELVE MONTH

Brief Scope of Consultancy

-

1. Lung Cheung Road and Ching Cheung Road Improvements investigation, design and construction supervision

12. Route 3 Country Park Sector

between Ting Kau and Au Tau ́- preliminary design and

preparation of bid package.

13. Central Kowloon Route

Expected

Managing Department

Commencement Date (Officer In-Charge)

October 1990

January 1991

Highways Department

|(Mr J M Turner - 573 3885)

Environmental Protection Department

– EA/EIA studies only (Mr W J Farrell - 835 1102)

Highways Department

(Mr H S Kwong - 733 2508)

January/February

Feasibility Study

1991

4. Green Island Link Feasibility

Study

February 1991

5. Route 3 Tsing Yi Sector

between Lai Chi Kok and Ting Kau - detailed design

6. Route 16 Feasibility Study

May 1991 (if it

were decided not to

privatize this sector.)

June 1991

(May be advanced to October 90)

Highways Department |(Mr J M Turner - 573 3885)

Highways Department

(Mr J M Turner - 573 3885)

Environmental Protection Department

- EA/EIA studies only |(Mr W J Farrell - 835 1102)

Highways Department |(Mr H S Kwong – 733 2508)

Highways Department (Mr H S Kwong - 733 2508)

NEW AIRPORT AND RELATED PROJECTS

LIST OF CONTRACTS AWARDED AT OCTOBER 1990

Civil

Engineering

Sito

Investigation

Managing

Expected

Contract

Brief Scope of Contract

Contract awarded Officer In-charge

Contractor

Contract

Suma

($million)

Completion

Date

|24 August 1990

Civil Engineering Services Department (Mr M S Leung - 368 9768)

Gammon Construction

234

19 June 1992

-

Lid.

1. Contract of Yau Ma Tei

Replacement Typhoon Shelter, Phase I (Contract No.

CV/90/04 - construction of a 1,400m long breakwater, 500m seawall and 4.5ha

reclamation for the new 70ha typhoon shelter which is to

enable the existing typhoon shelter be released for land

formation for construction of the airport-related transport projects and other developments.

1. Route 3-site investigation

for tunnels at Tsing Yi.

5 September 1990 Highways Department Gammon

14

4 March 1991|

(Mr H S Kwong ~ 733 2508)

Construction Lid.

-

END