20.

V.

Failure to provide an additional parallel north-south

transport link in Kowloon on the Reclamation would

require that this be built separately at additional

cost.

vi. Construction of the entire project on BOT basis would

provision of

of vital

unnecessarily put at risk the

strategic facilities.

1997.

In sum, Mr. Wu's Proposal would require significant

additional expenditure prior to the airport opening in

Equally important, the cash flow required would be

heavily front-end loaded and therefore unattractive,

especially on the proposed BOT basis. Mr. Wu's Proposal is

silent on the potential Government support and assurances

that might be required.

Programming

21. In order to develop a programme for Mr. Gordon Wu's

Proposal, comparable to that for the core PADS projects the

construction periods identified by Mr. Wu in his report

have been adopted and certain assumptions regarding

duration of the front-end activities have been included.

The latter provide for all the various alignment studies,

site investigations, committing investors and lenders, and

Governmental approval processes which would be required

prior to competitive bidding for either a Government or a