19.
b. PADS Projects
i.
Final design consultants have been selected for
all of the core PADS projects and many are in the
final design stage. Construction has already
commenced on the initial phase of the West
There is less risk of any
Kowloon Reclamation.
significant delays in the completion of the
projects.
ii.
The earliest that direct land access needs to be
provided to N. Lantau is in the early to late
1996. Due to the large scale of the Chek Lap Kok
Airport and the North Lantau community
construction projects commencing in late 1991, it
will be necessary that comprehensive ship and
barge delivery systems, as well as construction
camps, be established to support these activities
from that point in time until their completion.
Financial Performance
Gordon Wu's
In view of the conceptual nature of Mr.
Proposal it is extremely difficult to develop meaningful
financial comparisons. However, assuming comparable costs
for like elements, an attempt has been made to examine
likely cost implications of those areas where the proposal