IT STILL LEFT UNRESOLVED THE REASON WHY THE PROBLEM WAS NOT
APPRECIATED EARLIER. MR SHUM WAS TO CONDUCT AN INVESTIGATION INTO GEC'S CONTROL OF SUB-CONTRACTORS TO ENSURE THAT THE
PROBLEM DID NOT OCCUR AGAIN. HE WOULD ALSO BE INVESTIGATING THE ROLE OF GNPJVC AND EDF. IT WOULD NOT BE A WITCH HUNT. MR SHUM WOULD REPORT BACK TO BOTH GEC AND DTI IN EARLY JUNE AS TO HIS FINDINGS.
THE NEXT TWO WEEKS ARE CRITICAL. IF CBE CAN RISE TO THE OCCASION AND PUT IN THE NEEDED RESOURCES AT DARLINGTON IT IS FELT THAT THE TIMETABLE CAN BE KEPT TO. IT WAS AGREED BY ALL PARTIES (GNPJVC, GEC AND DTI) THAT PRESSURE WOULD BE MAINTAINED ON CBE.