FM BTC HONG KONG
TO PRIORITY PEKING
TELNO 130
OF 26030OZ JUNE 89
AND TO PRIORITY DTI, FCO, ECGD
PA
HKC 166
&
FCO FOR FED
DTI FOR ADAMS PEP, PALMER PEP3, GOODMAN EM4
ECGD FOR SEDMAN
DAYA BAY : GEC
1. DAY (DTI) AND CURRIE VISITED DAYA BAY 22 QUARTERLY JOINT CO-ORDINATION MEETING.
24 JUNE TO ATTEND
2.
STEPS TAKEN BY GEC TO OVERCOME THE CLEVELAND BRIDGE PROBLEM WERE ACKNOWLEDGED. GEC ESTIMATE THAT ANTI-WHIP RESTRAINT CAN BE COMPLETED TEN WEEKS BEHIND SCHEDULE AND WITHOUT SIGNIFICANT EFFECT ON POWER STATION COMPLETION DATE.
3.
BUT IT IS APPARENT THAT SERIOUS PROBLEMS REMAIN BETWEEN GEC AND GNPJVC. MANAGEMENT AT DAYA BAY ARE CONCERNED AT WHAT THEY PERCEIVE AS GEC'S INFLEXIBLE AND SLOPPY ATTITUDES TO PROVISION OF PLANNING DOCUMENTATION, DELIVERIES OF MATERIAL, QUALITY CONTROL, SUPERVISION OF SUB-CONTRACTORS AND OVERALL MANAGEMENT CONTROL. GNPJVC MADE IT CLEAR THAT THEY REMAIN CONCERNED OVER GEC'S WILLINGNESS TO CO-OPERATE EFFECTIVELY AT SUCH A LATE AND CRITICAL STAGE IN THE PROJECT'S EXECUTION.
5. DAY WILL REPORT FULLY ON RETURN TO LONDON IN THE WEEK.
HEAP