MIPT: DAYA BAY
*
1 FOLLOWING ARE THE MAIN POINTS OF COMPLAINTS RAISED BY GNPJVC, AS MENTIONED IN TUR:
A) LATE DELIVERIES, MISSING END OF MANUFACTURE REPORTS, BAD PACKAGING, MISSING PACKING LISTS: POOR QUALITY CONTROL.
B) FAILURE BY GEC MANAGER TO CONSULT OTHERS (IE GNPJVC OR SEPC)
IN TACKLING PROBLEMS.
C) LACK OF DTI MONITORING OF CONTRACT.
D)
LATE DELIVERIES OF BOP CRANES.
E)
F)
FAILURE OF ELECTRONIC CONTROLS ON TURBINE-HALL CRANE.
ALSO ON TURBINE-HALL CRANE: WRONG ASSEMBLY OF DRIVE GEAR-BOXES.
G) DAMAGE TO NUMBER ONE GENERATOR HWILE ON TEST, AND FAILURE TO OBTAIN SATISFACTORY ASSURANCES THAT QUALITY HAD NOT BEEN IMPAIRED.
H) FAILURE OF FEED PUMP WHILE ON TEST DUE TO OPERATOR ERROR
DURING ASSEMBLY.
I) POOR SCHEDULING OF DELIVERIES.
J) LATE, INACCURATE AND INCOMPLETE ENGINEERING DRAWINGS.
K) FAILURE TO USE IED PROPERLY.
DONALD