TNAG-1659-FCO40-2307-Hong-Kong-roads-and-traffic-legislation-1987 — Page 115

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

IMPLEMENTATION PROGRAMME

Private Sector Venture

1987

Apr

Gazetting of the invitation to make proposals.

Establishment of

Annex D

Public Works Project

1987-88

Apr 87-

Design Period

Jan 88

Feb 88-

Contract Tendering

July 88

Apr 88

Commencement of

May

Steering Group and Assessment

Teams

31 Aug

Deadline for

1992

submission of

offers.

mid

1 Sept-

Assessment/

31 Dec

1988

Jan

Negotiations.

Consideration

of recommend ations by

Members and

possible award.

Mar/Apr

Enactment of

Legislation.

May- June

Start of construction.

1992

Opening.

Construction

Opening

(Note: the above dates relate to the tunnel section which is the critical path.

design, tendering and

Parallel

construction will be taking place with respect to the approaches.)