TNAG-1658-FCO40-2306-Daya-Bay-nuclear-power-station-project-safety-concerns-in-Ho-1987 — Page 35

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

RESTRICTED

RESTRICTED

FM FCO

TO DESKBY 27010OZ HONG KONG

TELNO 3122

OF 26155OZ NOVEMBER 87

INFO PRIORITY PEKING

нис 16613

RECEIVED IN REGISTRY

27 NOV 1987

DESK OFFICER

INDEX

PA

REGISTRY Action Taken

001006

MDHOAN 3800

TOP

DIS

PQ: DAYA BAY

1.

WE HAVE BEEN ASKED TO PROVIDE A DRAFT REPLY TO THE

FOLLOWING WRITTEN QUESTION FROM HARRY COHEN MP.

QUOTE: TO ASK THE SECRETARY OF STATE/HMG: PURSUANT TO HIS ANSWER OF 26 OCTOBER, WHAT REMEDIAL ACTION WILL BE TAKEN TO ENSURE THE SAFETY OF THE DAYA BAY POWER PLANT SEMICOLON, WHO HAS BEEN IDENTIFIED AS RESPONSIBLE FOR THE OMISSION OF THE REINFORCEMENT BARS FROM THE FIRST CONCRETE LAYER SEMICOLON, WHAT REPRESENTATION HE HAS RECEIVED FROM THE GOVERNMENT OF CHINA ON THE IMPLICATIONS OF THESE FAULTS FOR THE SAFETY OF LOCAL RESIDENTS UNQUOTE.

2.

WE PROPOSE TO ANSWER AS FOLLOWS:

QUOTE: ADDITIONAL BARS AND CONCRETE REINFORCEMENT HAVE BEEN PLACED IN THE SECOND LAYER OF THE UNIT ONE REACTOR RAFT. THE OMISSION OF BARS WAS DUE TO A WRONG INTERPRETATION OF TECHNICAL DRAWINGS BY THE CONTRACTOR, AND INADEQUATE ENFORCEMENT OF QUALITY CONTROL CHECKS. IMPROVEMENTS HAVE NOW BEEN MADE TO THE QUALITY CONTROL ARRANGEMENTS TO AVOID SIMILAR PROBLEMS IN THE FUTURE. I HAVE NOT RECEIVED ANY REPRESENTATIONS FROM THE GOVERNMENT OF CHINA ON THE IMPLICATIONS OF THESE FAULTS FOR THE SAFETY OF LOCAL RESIDENTS. UNQUOTE.

BUT

3. WE WOULD BE GRATEFUL FOR ANY COMMENTS THAT YOU MAY HAVE ON THE ABOVE DESKBY 271200Z. WE APOLOGISE FOR THE SHORT NOTICE,

OUR DRAFT BY NOON ON MONDAY 30

WE ARE REQUIRED TO SUBMIT NOVEMBER.

HOWE

YYYY