TNAG-1642-FCO40-2289-Public-finance-in-Hong-Kong-Supplementary-Appropriation-(198-1987 — Page 206

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

26.11.86

8.30 - 12.15 p.m.

Date:

Time:

Reporter:

MEP

1 hundred something thousand, but the related work because of the

finishing, has to be redone. Total $1.1 million.

2

3

45

CHAIRMAN:

$1.1 million. Has that been approved?

6

D of Ar. S:

Yes.

141

7 ∞ a

8

CHAIRMAN:

And the work has been going on?

9

10

D of Ar. S :

Oh yes.

11

12

CHAIRMAN:

13

14

D of Ar. S :

When do you expect to complete?

March 1987.

15

16

CHAIRMAN:

March 1987?

17

D of Ar. S:

18

Yes.

19

20

CHAIRMAN:

21

22

23

24

25

There is one technical question I wish to ask on para. 144. After this whole stadium is constructed that you find

a problem with the water leakage, and then now there is a proposal of fixing the problem with $1.1 million with internal waterproof tank, then why in paragraph 144 where you say 'As for tanking, the cost of

the building construction will be double'.

26

27

D of Ar. S :

It is double. It would have been double.

28

29

CHAIRMAN:

How much will it cost to construct that?

30

31

32

33

34

35

36

D of Ar. S: As I mentioned earlier, the Government has spent a total of $2 million for remedial work. In other words, the basement, the leaks, to cure it, but had the Government decided to use the tanking and not accept the consultant's proposal relying so to speak relying on waterproof concrete, the cost would have been $4.8 million.