"powered mechanical equipment" has the same meaning as in the

Ordinance;

"restricted hours"

means the times during which Construction Noise

Permits may apply as specified in the Ordinance,

that is, between

1900 hours and 0700 hours on any two consecutive days and at any

time on general holiday, including Sunday;

"site boundary" means the boundary of a construction site as

specified in a Construction Noise Permit; and

"work" has the same meaning as in the Ordinance.

Standard

acoustical

terminology

is used throughout

this

Technical

Memorandum. Other terms are as defined in the Ordinance or in the text

of this Technical Memorandum.

1.4 General Introduction to the Procedures

For the purpose of assessing if a Construction Noise Permit may

be issued for work other than percussive piling during restricted hours

the Authority shall act in accordance with the following general

procedures which are detailed in subsequent sections. The Authority

shall :-

(a)

(b)

identify the most affected Noise Sensitive Receiver, determine

the Area Sensitivity Rating for the area within which the Noise

Sensitive Receiver is located and hence determine the relevant

Acceptable Noise Level

Level (in accordance with Sections 2.1 to

2.6);

calculate the Corrected Noise Level which will be generated by

the work at the Noise Sensitive Receiver (in accordance with

Sections 2.7 to 2.12); and

(c)

compare the

Corrected Noise Level with the Acceptable Noise

Level to determine if a Construction Noise Permit may be issued

(in accordance with Section 2.13).