10
(A)
Introduction
A Plan and scheme for the New Territories
Circular Road, Improvements project, Au Tau to Fan Kam Road
giving details of the proposed road works, land
requirements and requirements for other rights were
prepared in accordance with Section 5 of the Roads (Works,
Use and Compensation) Ordinance (hereinafter referred to
as "the Ordinance") and made available for public
inspection, and a notice (GN 3453) calling attention to
the plan and scheme was gazetted in accordance with
Section 8 of the Ordinance on 29 October 1982. Following
receipt of objections to the proposal, the Secretary for
Lands and Works had obtained authorization from the
Governor in Council for a modified plan and scheme which
were made available for public inspection and a notice (GN
3733) calling public attention to this was gazetted under
Section 11 (9) (d) of the Ordinance on 25 November 1983.
Owing to modification of the scheme, a section of
the route at Chuk Yuen Tsuen between Sheung San Wai and
Yau Mei San Tsuen was omitted from the scheme. Following
an engineering study, the route at the omitted section is
to be realigned further to the east of Castle Peak Road
and the plans and scheme have been prepared for the
construction of that section and is the subject of a
separate gazette notice.