NEW TERRITORIES CIRCULAR ROAD IMPROVEMENTS

AU TAU TO FAN KAM ROAD PHASE 3 FAIRVIEW PARK TO MAI PO (PART)

SECTION FROM SHEUNG SAN WAI TO YAU MEI SAN TSUEN

Objection to Government Gazette Notice 2407 on 18.7.86 (Closing date for objections 16.9.86)

SERIAL NUMBER & DATE

NAME OF OBJECTOR

BRIEF

DESCRIPTION

OF OBJECTION

HyD's

INTERPRETATION OF VALIDITY

HyD's COMMENTS AND WHETHER

SCHEME SHOULD

BE AMENDED

CLARIFICATION

FROM OBJECTORS REQUIRED

WHETHER LEGAL

ADVICE

REQUIRED

1

12.8.1986

Madam WONG Yiu-mui & Mr. WCNG Kwok-kei

The objectors considered that the proposed limit of works area is too close to their house and requested for the limit to be shifted.

The objection is considered valid as the proposed limit is very close to the external wall of the house.

In order to alleviate the situation, the limit of works area should be slightly modified if possible.

The objectors welcomed the proposed modifications as shown on drg. No. NH 6153B and submitted a letter of withdrawal to their previous objection.

No.

WHETHER CONSULT-

Yes.

ATION WITH OTHER

This has been carried out with DLOL,

DEPARTMENTS