(b) the identity of any contractor or sub-contractor

engaged in the project and the terms of any

contract with him other than such terms as are

described in proviso (a) of section 28;

(c) any other matter relevant to the project,

and the Road Company shall comply with the notice within

the time specified therein, being a time reasonable in the

circumstances.

(2) The Director may in relation to the carrying out

of the construction works by notice in writing to the Road

Company require it to take such steps as may be specified

in the notice for

(a)

the safety of any works including the guarding

and lighting thereof;

(b) the avoidance or abatement, whether in part or in

whole, of nuisances;

(c)

the protection of the environment;