TNAG-1515-FCO40-2076-Bridges-and-tunnels-in-Hong-Kong-1986 — Page 328

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

CONFIDENTIAL

3

Annex C.2

(Cont'd)

Inflation

3.

Inflation is taken at 6% per annum throughout the period.

Finance costs

4.

One hundred per cent loan financing is assumed with interest

set at 8.5% per annum on the outstanding balance annually.

Capital cost cashflow

5.

At 1986 prices construction costs are assumed to have the

following profiles

-

Two tubes together

Phased

construction

Remarks

($: million)

($ million)

1986

50.0

40.0

1987

120.0

100.0

1988

140.0

120.0

1989

120.0

90.0

1990

60.0

20.0

1st tube or both tubes in operation mid-1990

1991

10.0

5.0

1992

25.0

1993

55.0

1994

65.0

1995

20.0

2nd tube in operation

mid-1995

1996

5.0

Total

500.0

545.0