he may direct the Road Company to discontinue work on any

such part of the construction works and to remove any such

construction works or plant, either forthwith or within

such time as he may specify, and work on such construction

works shall not be resumed except with the prior permission

of the Director and subject to such conditions as he may

impose.

(3) If the Road Company fails to remove any works or

plant in accordance with a direction under subsection (2)

the Director may do so.

(4) Where the Director carries out any works under

subsection (3), the cost of so doing shall be recoverable

by the Government as a debt owing by the Road Company to

the Government.

Restoration of sea-bed and works

area.

33. (1) On the completion of the construction works,

as soon as is, reasonably practicable thereafter, the

Road Company at its own expense and to the reasonable

satisfaction of the Director shall