TNAG-1506-FCO40-2064-Guangdong-nuclear-power-station-project-at-Daya-Bay-safety-c-1986 — Page 140

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

(b)

(c)

planning will be presented in a manner likely to be intelligible to non-technical readers and shall thereafter write the summary report.

The summary report shall be submitted to the HKG within 3 (three) months of the submission of the report on the revised ERL's or of notification that comment on revised ERL's is not required provided sufficient liaison between the HKG and the consultants can be arranged during this period.

The consultants shall make a two man-visit to Hong Kong to discuss the summary report at a late stage in the drafting (additional to the visits referred to in 4.2.6).

MODIFICATIONS TO SECTION 6

DOCUMENTATION

Page 11, replace (d) as follows:

(d)(1)

OR (d)(ii)

report on the extension of the initial accident assessment study to be submitted to the HKG within 18 (eighteen) months of the submission of the report referred to in paragraph 6(c). (Study B second phase)

<

report on the extension of the initial accident assessment study to be submitted to the HKG within 14 (fourteen) months of the submission of the report referred to in paragraph 6(c). (Study B - second phase reduced)

-

Add to (f) as follows:

The summary report to the outline contingency plan to be submitted to the HKG within 3 (three) months of receipt of information from the HKG on the necessity for the provision of revised ERL's.