TNAG-1502-FCO40-2060-Guangdong-nuclear-power-station-project-at-Daya-Bay-safety-c-1986 — Page 34

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

GPS 250

RESTRICTED

FM HONG KONG

TO IMMEDIATE FCO

TELNO 2621

OF 1403OCZ AUGUST 86

RESTRICTED

YOUR TELNO. 1704 : DAYA BAY : MEETINGS WITH HARWELL CONSULTANTS

THE HONG KONG TEAM COMPRISING UP. J.A.S. WILSON (ECONOMIC SERVICES

BRANCH), MR. G.J. OSBORNE (ELECTRICAL AND MECHANICAL SERVICES

DEPARTMENT) AND DR. M.C. WONG (POYAL OBSERVATORY) WILL CONTACT

MR. LEEKS DURING THE WEEK BEGINNING 15 AUGUST TO ARRANCE 4

CONVENIENT TIME TO CALL ON HKD APOUND 22 AUGUST.

2. FOR YOUR INFORMATION, THE ITINERARY FOR THE HONG KONG TEAM

IS AS FOLLOWS

<<

HK TEAM LEAVE FOP THE UK

15 AUGUST

16 AUGUST

HK TEAM ARRIVE LONDON

17 AUGUST

HK TEAM TRAVEL TO OXFORD

18 AUGUST

19 AUGUST

20 AUGUST

21 AUGUST

HK TEAM MEET MR. ALAN NEAL, MR. MARK DAVIES,

MP. PETER SAUNDERS AND DP. SPIAN WADE FOR DISCUSSION

ON CONTINGENCY PLAN REPORT

FURTHER DISCUSSION OR CONTINGENCY PLAN REPOPT

HK TEAM TRAVEL TO CULCHETH

HK TEAM MEET OP. PILL XIYON PR, LAN CODY AND

DR. WADE FOR DISCUSSION ON ACCIDENT ASSESSMENT

STUDIES

FURTHER DISCUSSION ON ACCIDENT ASSESSMENT

HK TEAM TRAVEL TO LONDON

23/24 AUGUST HK TEAM RETURN TO HK.

RESTRICTED

/3.