JUL 16 '86 17:03 TIBCOOL) HK GOVT

!་་

WTR for the week ending 11.7.86 from DO(S)

P.3

(D) Daya Bay

13.

Many people

Fears have not been dispelled by the departure of SES to Europe or by the proposed LegCo visit. see these as rather pointless.

14.

DB members had a frank and interesting discussion with China Light and Power officials during the visit to

They were surprised Castle Peak Power Station on 3rd July. to learn that Daya Bay is only intended as a stop-gap, between 1992 and 1995, and that CLP will need to have another new power station in operation in 1996. that this fact weakened the case for Daya Bay.

They felt

15.

CLP cannot provide a representative for today's DB meeting, so discussion of the subject will be deferred to 7th August (although the Company may still be unable, or willing, to send an expert then).

18.

Worshippers

The Catholic Diocesan Affairs Committee is organising a petition against. the power plant. were invited to sign when leaving churches in Southern last Sunday. There were long queues.