3.
2 -
These electrostatic precipitators are expensive;
they are estimated to cost about $130 million. The question
of whether interim measures involving costs of this
magnitude can be justified has been extensively discussed
within the Government and I expect an early decision as to
whether the upgrading of the project should be proposed to
the Public Works Sub-Committee.
4.
If it is decided to go ahead with the precipitators
work should start in the 1986/87 financial year and some
improvement would be achieved almost immediately as the
first of the two plants would be closed down for the
installation work to begin. The work should be completed
by 1990. On the other hand a decision not to instal
precipitators and to rely on transfer stations would mean
that the incinerators could not be closed down until 1989
at the earliest, although some improvement might be effected
before then by the use of barges to transport refuse to the
controlled tips.
No comments yet.
Private notes are available after approval.