Secretary for Lands and Works replied in Cantonese :

-

閣下在鄉村地區實施公共照明計劃的進 新界已經發展的地區或市區緩

慢,因為在決定敷設電纜線之前,必須首先 和沿線的鄉民詳細磋商,這個程序,可能需 時幾個月。磋商完畢之後地政署才可發出 掘地許可證給予電力公司進行施工。

(The following is the interpretation of what the Secretary for Lands and Works

replied.)

Sir, Public Lighting Programme in the village areas is indeed slower than that

in the urbanised areas of the New Territories or urban areas because before the

wires are laid the proposals have to be discussed in detail with the residents

there. This may take several months to complete and only upon the completion of

the negotiations can the Lands Department issue a permit to the contractor to

actually proceed with the installation.