Subject
Purpose
Progress Made & Present Position
Target for Next Quarter
10.
New Territories
Co-ordination Committee
To co-ordinate social and physical development in the New Territories.
The Committee met on 9.8.82 and 18.10.82. Major issues which have been examined include, inter-alia :
(a) urban improvement and/or renewal scheme for Tsuen Wan Central Area;
(b) provision of community
facilities in temporary housing areas;
(c) slope remedial works.
To continue a systematic examination of impending development in the New Territories districts to ensure proper community facilities are incorporated in the development process and that deficiencies are being rectified.
CONFIDENTIAL ##
11.
Urban Area Co-ordination
Committee
To co-ordinate social
and physical development in the Urban Area.
Departments have taken follow-up action as a result of the last meeting and have submitted papers on
-*
(a) Lei Yue Mun Barracks
Development;
Current
(b) Western Reclamation
Development Proposals and Interim Land Utilization;
(c) Delays in PSPS/MIH
for future discussion.
To examine the following items :
(a) General development
in Hong Kong;
(b) Temporary and permanent
land use for Western Reclamation;
(c) Delays in PSPS/MIH
Projects.