TNAG-1140-FCO40-1420-Quarterly-progress-reports-on-Hong-Kong-1982 — Page 127

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

CONFIDENTIAL

機密

7.

Subject

Land Use and Transport Optimisation

Study

Purpose

To develop a computer based model and use it in determin- ing the Land Use-Transportat ion pattern that will yield the greatest benefit accord- ing to stated criteria.

- 6 -

Progress Made & Present Position

Next Quarter Targets

(a) The main computer programme for the

LUTO model was completed on schedule in September.

(a)

(b)

(c)

(a)

Of the studies providing cost data input to LUTO, the North East New Territories Study is complete in draft, the North Western New Territories Study is proceeding according to its (extended) schedule, and the Strategic Harbour Reclamation and Urban Growth Study (SHRUG) is on schedule. The North Lantau Development Investigations (Phases 2A & 2B) have been approved in principle by LDPC to start as a consultancy study before the end of the year, but funds are still being sought. The lead time for data on North Lantau lies on LUTO's critical path, and data may have to be synthesised to permit completion within the time scale.

Maximal highway and public transport networks have been prepared and agreed.

With cost data input as the most critical issue it appears that the 'Phase 1 LUTO Solution' will be postponed from March to July 1983.

(b)

Continue with the

development of the model and the processing of the studies.

Continue with detailed and critical appraisal of LUTO to facilitate the processing of the findings in future.

GF 323

CONFIDENTIAL ##

CONFIDENTIAL

機密

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.