TNAG-1139-FCO40-1419-Quarterly-progress-reports-on-Hong-Kong-1982 — Page 42

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

Subject

3. Additional

Harbour Crossing Facilities, Study of Options

(Cont'd)

CONFIDENTIAL

機密

friduani

38

CONFIDENTIAL #2

Purpose

To regulate the cost, level and standards of services of taxi operations.

Progress Made & Present Position

(b) The working group considering possible arrangements for the finance and management of the bridge has concluded that unacceptable delays would result if the Lyemun Bridge project was the subject of international tender. The project might be expedited by approaching a small number of companies with the

expertise for construction and management of the bridge. To this end the Cross Harbour Tunnel Company has been approached.

.

(c) An interim report on the

feasibility of the bridge, its location (as dictated by Airport flight path and Marine clearance but not I.L.S. considerations) and the type of structurę has been received.

(a)

Tender premia for urban and N.T. taxi licences in the May tenders rose by 1.9% and 39.6% respectively compared with the February tender)

(b) Following applications from the

taxi associations, the Transport Department has made recommendations that taxi fares be increased. These will be examined by TAC on 6 August.

(b)

•(c)

Next Quarter Targets an

To keep ExCo informed about developments.

Consider the response

to the Company in the light of the findings of the interim report.

(a) Keep TAC and ExCo

informed of aspects affecting the cost, level and standards of service:

(b) Submit to ExCo.

4. Taxi

Operations

(CR 3/5591/71 VI)

Comments