TNAG-1139-FCO40-1419-Quarterly-progress-reports-on-Hong-Kong-1982 — Page 173

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

4

Councils and Administration Branch Progress Report

(1 February 1982 30 April 1982)

Subject

Purpose

CONFIDENTIAL ##

Note

Progress Made & Present Position

Next Quarter Target

(b) NDO Construction - a joint-venture

development programme is underway to build

1365 new quarters of all grades by 1985/86. 17 joint-venture projects have been tendered and are underway and a further 4 are under active planning for implementation in 1982/83. A further 168 quarters are being built at Mt. Butler under the PWP.

Monitor redevelopmen programme and find

new sites to maintain impetus.

(c

CONFIDENTIAL #

Purchase

***

approval has been given by FC for the purchase of 150 quarters to help overcome the immediate NDQ shortfall.

Identify suitable quarters and effect purchases.

w.e.f. 1st April, Management Services Division became part of Finance Branch and so items (4), (5) and (6) of the last quarterly report will feature in the Finance Branch Report.