APPENDIX
2 x 300kw transmitters, installation
cost, spares, valves
CHE HA
TSANG TSUI
EK
ΕΚ
1,750
1,750
4 x 4 band aerial arrays
240
240
Feeder system
100
120
Towers, building, site work
1,703
1,810
1
Power Equipment
426
426
Capital contribution for the
186
681
electricity supply; main plus
reserve
Control system
100
100
Capital contribution for programme
circuit
200
Freight, insurance, transport
200
250
Staff costs
300
300
Travelling, expenses, site
200
220
accommodation
Cost of land resumption and
610
435
compensation
TOTAL
5,815
6,532
Expenditure pattern
Year 1
1,800
Year 2
2,015
Year 3
2,000
Year 4
0
30 months
600
1,500
2,400
2,032
30 months
:
Timescale of completion of project:
* The Tsang Tsui project would take 30 months from completion of access road which is scheduled for 1982 but could be earlier we understand if this site were were chosen.
CWD/SJS 30.10.80