TNAG-0962-FCO40-1181-Possible-new-airport-for-Hong-Kong-1980 — Page 101

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

TENTATIVE OUTLINE PROGRAMME OF NORTH LANTAU DEVELOPMENT, REPLACEMENT AIRPORT AND LANTAU FIXED CROSSING

ANNEX B TO XCC(8,70

1979 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993

ACTIVITIES / WORKS

(A) STAGE I NORTH LANTAU DEVELOPMENT

1

2

INVESTIGATION [NDE 19(1)]

ان

PROJECT APPROVAL (INCLUDING SUBMISSION OF REPORT TO NLDSG, PWDC, LDPC AND CREATION OF PWP ITEM)

FOR DESIGN FOR CONSTRUCTION

3. TRANSPORT STUDIES

STAGE I

STAGE II

4. FURTHER STUDIES (INCLUDING HYDROGRAPHICAL, DETAIL/ SPECIAL

SITE INVESTIGATION

5. DETAIL DESIGN

6. CONSTRUCTION

*

AND LANDSCAPING )

(B) STAGE II(1)* NORTH LANTAU DEVELOPMENT

1 INVESTIGATIONS [NDE 19 (1)]

2 PROJECT APPROVAL (INCLUDING SUBMISSION TO NLDSG, PWDC AND LDPC

AND CREATION OF PWP ITEM)

3. FURTHER STUDIES (INCLUDING HYDROGRAPHICAL, DETAIL/SPECIAL SITE

INVESTIGATION AND LANDSCAPING)

4. ACCESS ROAD TO AIRPORT (DESIGN AND CONSTRUCTION OF PRIMARY

DISTRIBUTOR ROADS)

5. DETAIL DESIGN

6. CONSTRUCTION

着物 WITH REPLACEMENT AIRPORT AT CHEK LAP KOK)

(C) REPLACEMENT AIRPORT

1. ROYAL OBSERVATORY STUDIES

2. REPLACEMENT AIRPORT CONSULTANCY

3. OVERALL APPRECIATION OF IMPLICATIONS (A) INITIAL ASSESSMENT

4. FINANCIAL VIABILITY

IB) FINAL ASSESSMENT

5. CO-ORDINATION OF VARIOUS STUDIES FOR SUBMISSION TO ExCo

6. AIRPORT MASTER PLAN

7. CIVIL ENGINEERING DESIGN (INCL. SITE INVESTIGATIONS & TEST FILL

EMBANKMENT)

}

8. CO-ORDINATION OF VARIOUS STUDIES FOR SUBMISSION TO ExCo APPROVAL FOR CON- 9. AIRPORT LAND FORMATION

10. CONSTRUCTION OF AIRPORT BUILDINGS, RUNWAY & APRON

11. EQUIPMENT INSTALLATION

STRUCTION

12. TRANSFER OF OPERATION FROM KAI TAK AND CLOSE DOWN OF KAI TAK

13. DESIGN & CONSTRUCTION OF PHASE 2(SECOND RUNWAY & SUPPORTING FACILITIES) (D) LANTAU FIXED CROSSING

1. CONSIDERATION OF CONSULTANTS' REPORT BY GOVERNMENT

2. FURTHER STUDIES & ADDITIONAL REPORT

3. CONSIDERATION OF ADDITIONAL REPORT

4. DETAIL DESIGN AND CONTRACT STAGE (INCLUDING SITE INVESTIGATION

CONTRACTS, SPECIAL TESTS) [i.e. AERODYNAMIC & MATERIALS)

5. PRE-CONTRACT ACTIVITIVES

6. PROJECT APPROVAL FOR CONSTRUCTION

7. CONSTRUCTION OF H.O. WORKS

8. CONSTRUCTION OF N.T.D.D. WORKS (INDICATING LATEST POSSIBLE START DATE

CONSISTENT WITH COMPLETION IN LINE WITH H.O. WORKS)

(E) FINANCIAL PLANNING

1. PREPARATION OF AN OVERALL FINANCIAL PLAN FOR THE NORTH LANTAU

DEVELOPMENT PROJECTS

DATE : MAY 1980

FOR DESIGN FOR CONSTRUCTION

LAND BECOMING AVAILABLE (WITH SERVICES)

LAND BECOMING AVAILABLE (WITH SERVICES)

ExCo DECISION ON FURTHER PLANNING/INVESTIGATIONS

EXCO DECISION ON CONSTRUCTION

EXCO INFORMED OF CONSULTANTS' RECOMMENDATION

TENTATIVE

COMMENCEMENT OF OPERATION ON PHASE 1

(SINGLE RUNWAY}

ExCo DECISION ON CONSTRUCTION

COMPLETION (BASIC 4 LANES WITH ALLOWANCE FOR LATER

EXPANSION TO 6 LANES }

ENVIRONMENT BRANCH, GOVERNMENT SECRETARIAT