Table 2 gives annual local and foreign currency requirements. The total amounts for 1978 and 1979 (as given in Table 2) include access road construction costs not allocable to the airport account. The construction cost of the road from the new airport to the first bridge is fully allocable to the airport account; however, only 20% of the construction costs of the bridges, interchanges and improvements to the eastern trunk roads are allocable to the airport account. As a result, only HK $276 million of the total of HK $632 million for access roads shown in Table 1 are allocable to the airport account. The remaining nonallocable access road expenditures of HK $356 million occur in 1978 and 1979, reducing the amounts allocable for these years to HK $461 million for 1978 and HK $508 million for 1979.
Table 2- New Airport Construction Costs by Year in Foreign Exchange and Local Currency (January 1974 HK $ Millions)
AMP-
Year
Foreign Exchange
Local Currency
Total
1975
6
5
11
1976
27
10
37
1977
110
60
170
1978
295
240
535
1979
412
378
790
1980
468
442
910
1981
476
465
941
1982
141
93
234
1983
137
89
226
1984
95
68
163
Total
2,167
1,850
4,017