Crown rent

:

$2,000 p. a.

User condition

Premium

Development condition

: For coal and/or oil fired electricity generating stations and associated plant and buildings together with such oil storage and coal storage facilities as are necessary to fuel the stations and such ancillary offices and staff quarters as may be approved by the Secretary for the New Territories.

: Between $200 million and $225

:

million, with a downpayment of about $100 million, the balance payable by 10 equal instalments including interest at 10% per annum (see also paragraph 19 below).

The area of road coloured green and hatched black on the plan at Annex A will be formed, drained, temporarily surfaced and provided with supporting structure where necessary to the satisfaction of the Director of Public Works.

Any piers shall be sited in accor- dance with the requirements of the Director of Public Works and/or the Director of Marine, and appropriate premia shall be payable in respect of the areas of sea bed so used.

Marine rights will be given between the points 'A' and 'B' on the plan at Annex A and shall endure for as long as the site is used for the above purposes.

As Government cannot guarantee to provide a water supply during the initial stages of development the provision of such supply will be the responsibility of the grantee.

Piers

:

Marine rights

:

Water supply

:

C.S. 166

CONFIDENTIAL ##

機密

Page 90Page 91

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.