TNAG-0740-FCO40-944-Quarterly-progress-reports-from-Hong-Kong-1978 — Page 78

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

CONFIDENTIAL

Subject

Purpose

Progress Made & Present Position

Part I

DIPTRANS

Development

of an Integrated

Fublic Transport System for 1980.

(CR 9/5591/77)

To study the changes in other public transport modes required as a result of the opening of the MIS of the MTR and the electrification of the KCR.

The third and fourth meetings of the Steering Group were held on 31st August and 5th October respectively to discuss Monthly Progress Reports and Interim Reports 2, 3, 4 and 5 produced by the Consultants.

Continue to monitor

progress on the basis of interim and monthly consultants' reports.

GF 323

Next Quarter Targets

機密

CONFIDENTIAL

Comments