密
CONFIDENTIAL #
SUBJECT
(ENV 40/25/28)
PURPOSE
ENVIRONMENT BRANCH PROGRESS REPORT
1ST AUGUST 1976 TO 31ST OCTOBER 1976
PART II IMPORTANT ISSUES
PROGRESS MADE & PRESENT POSITION
NEXT QUARTER TARGETS
28. K.C.R.
(TC 38/75)
(CR 13/3096/74)
(CR 55/5591/74)
To decide on an investment programme for the next five years.
(a) Investigation into the proposed
double-tracking of Beacon Hill Tunnel is continuing;
(a) Clear F.W.S.C、 paper
on paving;
機
(b) Progress discussions
on Beacon Hill Tunnel.
29. Tuen Mun New Town
(ENV 40/12/12)
To decide the internal public transport requirements for Tuen Mun New Town.
(a) The Stage II Engineering report on
Tuen Mun has been completed by Scott Wilson Kirkpatrick & Partners;
G.F. 313
CONFIDENTIAL